In this damages case against electric company PacifiCorp, plaintiff property owners seek to recover for losses they say they suffered in the widespread, 2020 "Labor Day Fire" in Oregon. A jury in an earlier case found defendant responsible for the fire because defendant failed to deactivate its power lines during a severe wind storm, causing the lines to ignite. Defendant maintains they had no duty to deactivate the lines.
| Description | Attorney | Witness | Witness Expertise | Presence | |||
|---|---|---|---|---|---|---|---|
![]() | 00:00:00 | General Case Activities | |||||
![]() | 00:12:47 | Opening Statement | Daniel, Adele | ||||
![]() | 00:47:37 | Opening Statement | Wilson, Harry | ||||
![]() | 01:05:39 | End of Session |
Recording Disclaimer: This proceeding was recorded in full.